Contractor timesheet approvals when the job code is wrong

Follow a timesheet correction from site supervisor to finance. A worked NZ example covers job costing, travel time, billing exceptions and authorised sign-off.

A survey technician checks time allocated to two jobs in timesheet software.
AI-generated editorial image.

A survey contractor works at two council sites on the same day. At the depot, they discover that they charged their entire afternoon to the library refurbishment. The total hours are right, but the library budget is carrying work done at the pool. Before buying timesheet software, ask a supplier to show how a supervisor can correct that allocation and explain the result to finance.

Which hours belong to which job?

For a demonstration, give the surveyor a Monday timesheet with three hours at the library, four at the pool and one travelling between sites. The example contract charges site hours to the relevant job and covers travel in a fixed fee. The cost report should therefore show all eight hours of effort, while the proposed hourly charges cover seven. Check the agreement for your own jobs before choosing a billing rule.

Ask the surveyor to record the date, assignment, job code, time spent and a brief description of the work. Let them save an unresolved allocation if the correct job code is missing. Assign it to the person who maintains project codes. A compulsory field with no usable choice invites staff to book work against whatever project appears first.

Who can approve a correction?

Give the site supervisor a comparison showing the submitted entry and the proposed split. They can confirm which site received the work. The commercial manager may need to decide separately whether a charge falls within scope. New Zealand Government Procurement’s day-to-day administration guidance distinguishes checking invoices, monitoring costs and authorising payment. Identify who has each authority under the contract.

After approval, preserve what the surveyor submitted, what changed, the reason, and who authorised it. If both projects have different budget holders, ask the supplier to show what each sees. A library manager can review costs removed from the library job without receiving unrelated detail about the pool project. Let the contractor see the outcome and raise a query against the same entry.

Can finance reconcile an adjustment after close?

Run the example again with the library cost report already closed for the month. Ask finance how it wants to recognise a late adjustment. One approach is a linked transfer in the next open period, showing an equal credit and debit against the original work. The finance owner should decide the treatment and verify how the entry appears in each affected report.

Finally, send the approved transfer to a test accounting file twice. Compare the job totals, chargeable hours and correction references. The repeat transfer should result in a single effective adjustment, with enough information to identify a failed or delayed posting. Give the export to a contract manager who missed the demo and ask them to reconstruct the eight-hour day. If they need the developer to explain where the travel went, the handover still needs work.